← The full process

Phase 3

Delivery and Setup

Every Wolf home is delivered and installed on a foundation. Before it leaves the factory, the route, the foundation, the utilities, and the field crew all have to be ready.

Property evaluation →

Wolf handles the permits, construction, site work, delivery, and final cleanup for full-service projects. Our employees and project managers guide the work from start to finish. We confirm service availability and included work for your property in your agreement.

Timing, costs & responsibilities
Timing
Often 12 to 16 weeks for site prep, delivery, setup, and closeout
Cost context
Starting price by model in Washington and Oregon, then quoted for your property
Delivery and setup starting prices →
Process area
Phase 3

A modular home doesn’t always need a crane

Where access allows, our field crew backs the home toward its prepared foundation and slides it into place. A crane is another option when the delivery path or placement calls for a lift. We plan the method for your property before set day.

Driveway width, turning room, slope, ground conditions, trees and overhead utilities all affect access. A ground set still needs equipment, crew time and a prepared foundation. Your proposal identifies the delivery and installation work and any added placement costs.

See delivery and installation details →
Watch on YouTube

Setting a Model K in a Portland backyard

There wasn’t much room to work, so the crew planned a specialty set to get this one-bedroom Model K into a tight Portland backyard.

Watch on its own page: Setting a Model K in a Portland backyard
Watch on YouTube

How we set a home with a crane

A Wolf home lifted off the delivery trailer and set on its foundation. We use a crane when a lot can’t be reached the usual way.

Watch on its own page: How we set a home with a crane

Overview

What happens in this stage

Before delivery, we coordinate the route, staging area, foundation, utilities, and field crew. Delivery and setup are quoted for the property, including any extra trenching, well or septic work, or delivery requirements. In Washington and Oregon, Wolf employees handle factory production, site work, delivery, and installation on one project schedule. Farther out, we deliver and set the home and a local contractor handles the site work. Some properties or jurisdictions require third-party services such as surveys or septic design and installation.

Why it matters

Delivery and setup turns the finished module into a connected home. The starting range covers standard work; difficult access, longer utility runs, septic or well work, grading, and retaining can increase the cost.

Inside delivery and setup

Each stage of the work in order, with photos from Wolf projects.

  1. Excavation and site prep underway on a Wolf project lot
    1

    Site prep & excavation

    Our field crew clears and levels the building pad, handles the minimum tree trimming and removals, and excavates for the foundation. This is the first step that turns a raw lot into a buildable site.

  2. A concrete stem-wall foundation being prepped for the pour
    2

    Foundation & stem wall

    We form and pour a 6-inch concrete stem-wall foundation, two feet tall, to carry the home. A solid, level foundation lets a modular home perform like a site-built house for decades.

  3. Utility trenching dug to connect a Wolf home to services
    3

    Utilities & trenching

    We run roughly 100 feet of trenching to connect water, sewer or septic, and power to the home’s stub-outs. Anything beyond the standard run (a new well, septic system, or a long utility pull) is scoped and quoted up front.

  4. A finished Wolf modular home being transported to its site
    4

    Delivery day

    Your finished home leaves the factory ~92% complete and travels to your property. We plan the route and access ahead of time and check narrow streets, steep drives, trees, and overhead wires before the truck leaves.

  5. A crane setting a Wolf home section onto its foundation
    5

    The set

    Depending on the site, the home is either backed in on its trailer and slid onto the prepared foundation, or a crane lifts each section into place. Our own field crew runs the set from start to finish.

  6. Two sections of a Wolf home pushed together, with siding still open at the seam
    6

    Joining the sections

    For multi-section homes, the modules are pulled together and the “marriage line” is sealed, then the roof, siding, and exterior details are buttoned up so the seams disappear into one finished home.

  7. A finished deck and porch on a completed Wolf home
    7

    Decks, porches & walkways

    We build the porches, decks, steps, and any sidewalks or hardscape so the home is safe to enter and ready to live in.

  8. A finished Wolf home with grass grown in and final cleanup complete
    8

    Connections, cleanup & keys

    We make the final utility connections, complete closeout and inspections, grade and clean up the disturbed areas, and walk the finished home with you before handing over the keys and your warranty.

Steep, tight, and rural lots

For rural properties and islands, building the home in our factory moves framing, systems, and finishes off your land. We review the roads, slope, trees, and any ferry route when we prepare your quote. Site work and utility connections are still planned for your property.

The route in

We look at the roads and the driveway the truck will use. Narrow streets, sharp turns, and rural roads can change the route or the timing.

Overhead wires and trees

Power lines over the road or the yard can block the home or the crane. Branches may need trimming. The baseline covers the minimum trimming and the removal of trees up to 6″ in diameter. Anything more is added to your quote.

Slope and crane reach

On a steep lot or a tight backyard, a crane can lift the home over the obstacles and set it on the foundation. We plan where the crane can sit and how far it has to reach well before delivery day.

Gravel drives and ferry access

A long gravel driveway or a lot reached by ferry can still work. For an island lot, we plan the delivery around the ferry. When a driveway is too narrow for a normal section, we can split the home into more pieces and join them on site.

Watch on YouTube

Crane sets a home on a steep waterfront lot

A tricky crane set on a difficult waterfront property.

Watch on its own page: Crane sets a home on a steep waterfront lot
Watch on YouTube

A challenging delivery up a steep gravel driveway

Our field crew threads a home up a steep, narrow driveway.

Watch on its own page: A challenging delivery up a steep gravel driveway

Difficult access can add cost. We price it in your written quote after we have seen the site.

From site visit to keys

The hand-offs between you and the Field Team, in order, including the two delivery and setup payments and the paperwork you receive along the way.

  1. 1

    The Field Team schedules your Initial Site Visit (ISV)

    When it is time to begin site work, someone from the Field Team reaches out to schedule the ISV. That visit is where they determine the exact needs of your project. Depending on the crew’s schedule, site work can happen before or after your home is finished in the factory.

  2. 2

    Payment 5 and your D&S paperwork

    Payment 5, the 50% Delivery & Setup Deposit, is due at the ISV. It is based on the estimated site work in your agreement. You also receive the D&S Expectations Letter, the D&S Process Checklist, and the timeline for your site work and delivery.

  3. 3

    Site work, delivery, and set

    Excavation, the stem-wall foundation, trenching, then delivery, placement by trailer or crane, tie-downs, and the utility hookups. These are the stages shown above, run by our own field crew.

  4. 4

    Connections, testing, and final inspection

    Once the house is placed, utilities are connected and tested, and the jurisdiction’s final inspection is completed. The disturbed area is rough-graded and cleaned up.

  5. 5

    Walkthrough and Payment 6

    We do a walkthrough of the finished home with you. The last payment in the process, the 50% Delivery & Setup Closeout, is due at this point.

  6. 6

    Keys, binder, and warranty

    Then we hand you the keys. You also get a binder of brochures, pamphlets, and instructions on how to take care of your new home, and your 1-year warranty begins. As always, call with any questions.

What the baseline covers, and what is extra

The first list describes the installation work we review for your property. Items in the second list are added to the quote only when your property needs them.

Included in the baseline

  • Excavation: the minimum required for foundation placement
  • Foundation: 6″ concrete stem wall, 2′ tall
  • Trenching: 100′ of trenching, 2′ deep, connecting to existing utilities
  • Grading: rough grade of the area disturbed by trenching and foundation excavation
  • Tree and brush trimming: the minimum needed to get the house into its final location
  • Tree removal up to 6″ in diameter where required for placement
  • Delivery: standard, within 20 miles of Wolf Industries
  • Placement: in an area reasonably accessible by a standard delivery trailer
  • Final inspection, testing, and clean-up

Additional services that may be needed

  • Delivery outside 20 miles from Wolf Industries, priced per project
  • Tree protection
  • Deeper utilities
  • Additional trenching
  • Taller foundation
  • New well
  • New septic system
  • New PUD power service
  • Gas service
  • Propane tanks
  • Fence repair
  • Landscaping

Delivery and Setup in real life

More photos from Wolf projects. Click any photo to enlarge.

1 / 8

What Wolf is coordinating

Stage steps

  1. 1 Review route, access, staging, crane or equipment needs, and any site constraints.
  2. 2 Prepare site work, foundation, and utility plans around the approved project scope.
  3. 3 Deliver the home from the factory and set it on the prepared foundation.
  4. 4 Connect utilities, complete closeout items, and walk the finished home with the owner.

Deliverables

  • Excavation and a 6" concrete stem-wall foundation, 2′ tall
  • 100′ of 2′-deep trenching to connect existing utilities
  • Rough grading, minor tree trimming, and delivery within 20 miles
  • Placement, utility connections, final inspection, testing, and clean-up

The details that usually surprise people

Access, existing utilities, well or septic work, trench length, and delivery distance all inform the written scope.

Narrow streets, steep drives, trees, fences, overhead wires, ferries, and rural roads can shape delivery.

The foundation and utilities need to be ready before the home arrives.

This stage, answered

What does the delivery and setup price include?

In Washington and Oregon, standard delivery and setup has a starting price by model, listed on our cost page. The standard scope covers excavation, a 6" concrete stem-wall foundation, about 100 feet of trenching to connect existing utilities, rough grading, minor tree work, delivery within 20 miles of our factory, placement, utility connections, and final inspection, testing, and clean-up. Delivery over 20 miles from our Battle Ground factory is priced per project. Model M delivery and installation are quoted for the property. Outside those two states, we price delivery and set for each property. Your written quote confirms what is included.

What would make it cost more?

More complex sites add to the baseline: extra or deeper trenching, a taller foundation, a new well, septic system, power service, or gas, propane tanks, tree protection, fence repair, landscaping, difficult access, or delivery beyond 20 miles. We review your site and quote those specifics before you commit.

What is the ISV?

The Initial Site Visit. When it is time to start site work, the Field Team schedules a visit to determine exactly what your project needs. The 50% Delivery & Setup Deposit is due at the ISV, and you receive the D&S Expectations Letter, the D&S Process Checklist, and your timeline.

What has to be ready before the home arrives?

The route, staging area, foundation, and utilities all need to be coordinated ahead of delivery day. We plan access and crane needs early, especially for coastal, mountain, island, or long-distance sites.

What do I get when the project is finished?

After the walkthrough and the final 50% Delivery & Setup Closeout, you get the keys, a binder of brochures, pamphlets, and care instructions for the home, and a 1-year warranty. Warranty details and requests live in the Owner Portal.

Want the process mapped to your address?

Send the property address and what you want the home to do. We’ll work out the model, the permit path, what the site needs, and your next step.