Phase 2
Factory Production
How the home moves through controlled indoor construction at Wolf Industries in Battle Ground, Washington.
Overview
What happens in this stage
Your home is built indoors by the same team, out of the weather, on a set production sequence. Our line has several stages, each with a designated foreman and a team that specializes in that craft; a home spends about three days in each stage, and you get a weekly update on how your Wolf home is progressing while it is on the line.
Why it matters
Building indoors is why a Wolf home goes up faster and more consistently than a site build. We produce a new home about every three days, and yours leaves the shop ~92% complete (framed, wired, plumbed, finished, and ready to set) instead of sitting half-built in the weather.
Pre-production meeting
The pre-production meeting, minute by minute
About a month before your estimated production date (after permits are issued on a turn-key project), you meet with a Wolf specialist to finalize every detail of the home. Plan on 2 to 3 hours. This is where you choose paint colors, trim, countertops, and the rest of the Options Book.
- 1 Check in 5 min
- 2 Idea tour of the shop (if needed) 15 min
- 3 Initial expectations 5 min
- 4 Pricing and options: the house 30 min
- 5 Finish schedule 30 min
- 6 Permitting review 10 min
- 7 Change orders (if necessary) 10 min
- 8 Delivery and setup: deck and size 5 min
- 9 Receive the production deposit 10 min
- 10 Introduce your Production Manager 5 min
Agenda time: about 125 minutes, plus discussion — plan on 2 to 3 hours.
At the end of the meeting
At the end of the meeting we collect Payment 3, the 25% Production Deposit, calculated from the house choices in your agreement. Our planning team then creates a production binder with the floor plans and specs for your build.
Browse the Options Book first →Step by step
Inside factory production
Each stage of the work in order, with photos from Wolf projects.
-
1Framing
The home’s floors, walls, and roof structure are framed on the production line, square, plumb, and to the same IRC/IBC (International Residential Code / International Building Code) codes as a site-built house, just indoors and out of the weather.
-
2Mechanical, electrical & plumbing
Wolf employees run the wiring, plumbing, and mechanical systems while the walls are still open, then everything is inspected before it gets covered. These are the same rough-in stages as any well-built house.
- 3
Insulation
We insulate the walls and ceilings indoors at the factory, so the insulation stays dry while it goes in and gets inspected before the walls are closed up. Good insulation work is a big part of why a small home stays comfortable year-round.
-
4Roofing
The roof, gable or shed depending on your plan, is sheathed and finished in the shop, so the home arrives weather-tight and ready for the field crew to set.
-
5Siding & exterior
Lap siding, trim, and exterior details go on indoors, so the outside of your home is largely complete before it ever leaves the factory.
- 6
Sheetrock & drywall
Once inspections pass, the walls are closed up with sheetrock, then taped and mudded to a smooth finish. This is when the inside starts to look like a home.
-
7Paint, trim & millwork
Interior paint, door and window trim, and millwork are installed and finished in our dedicated finishing area.
-
8Flooring, cabinets, counters & appliances
Flooring goes down and cabinets and counters are set. If you chose our appliance package, those appliances are installed and tested; if you provide your own, the home is finished with the hookups ready. By the end your home is ~92% complete and ready to ship.
Included vs. extra
What goes into every Wolf home
The materials and methods behind the stages above. They are the same on every model before any upgrade is added.
Structure and systems
- 2×6 wall construction, with LVL (laminated veneer lumber) for extra rigidity
- PEX plumbing supply lines
- Romex wiring for a safe, efficient electrical system
- Batt insulation rated R-24 in the walls, R-30 in the floors, and R-50 in the ceiling (foam plus batts on shed roofs), meeting or beating the state energy code minimums (hypoallergenic batts available)
- Roughed-in HVAC (heating, ventilation, and air conditioning) ducting planned around the compact layout
- Built to the International Residential Code (IRC) and International Building Code (IBC)
- Internal QA plus third-party inspection before any system is covered; nothing proceeds until it passes
Exterior and finish
- Fiber-cement lap siding with corner boards (board-and-batten is an upgrade)
- Prehung front door with a keypad deadbolt, and double-pane low-E vinyl windows rated U-0.27
- Drip caps over every window and door; all trim joints caulked
- Smooth sheetrock, mudded, taped, and sealed before paint
- Flooring, cabinets, and countertops from the Options Book
- Shower and tub bases set in mortar for stability
- The mini-split heat pump installed and tested on every home, plus appliances if you chose the Wolf appliance package
- A final inspection before the home is released for delivery
More from the field
Factory Production in real life
More photos from Wolf projects. Click any photo to enlarge.
Checklist
What Wolf is coordinating
Stage steps
- 1 Confirm final plan, selections, production slot, and readiness for the factory build.
- 2 Frame the home and complete mechanical, electrical, and plumbing stages.
- 3 Install siding, roofing, sheetrock, paint, millwork, cabinets, and counters, plus the appliance package if you chose it or hookups if you are providing your own.
- 4 Prepare the unit for delivery while site work and foundation planning continue.
Deliverables
- Controlled indoor build
- Standard Wolf finish package and selected options
- Production milestone updates
- Home prepared for transport and set
Watch outs
The details that usually surprise people
Factory production can move quickly, so selections and payment timing need to be settled before the slot.
Site readiness must stay coordinated with the production schedule.
Financing should account for factory draws before the home is visible on site.
Common questions
This stage, answered
How long does the factory build take?
How complete is the home when it leaves the factory?
What is decided at the pre-production meeting?
How will I know what is happening during the build?
Can I make changes once production starts?
Want the process mapped to your address?
Send the property address and what you want the home to do. We’ll work out the model, the permit path, what the site needs, and your next step.