Free modular home & ADU cost calculator · No signup required
Free ADU (accessory dwelling unit) Cost & Modular Home Budget Calculator
Enter your address and lot details to see what every Wolf home costs on your property. Pick a home for its full breakdown. No signup required.
Just want the base home prices? →Explore your home budget and project timeline
Step 1 of 3: Your property
Or pick a common area:
County selection is a starting point. Confirm city limits and the actual delivery route for your parcel. Counties without a separate cost sample use the regional WA/OR benchmark.
Service area baseline
Washington & Oregon service area
Standard setup covers sites within 20 miles of our Battle Ground factory. Delivery over 20 miles is priced per project.
For full-service projects in Washington and Oregon, Wolf employees handle property review, home design, permits, factory construction, dirt work, foundations, utilities, delivery, installation, and final cleanup. Our project managers coordinate the work, and Wolf handles warranty concerns after move-in. The work we can handle depends on your property, delivery access, local building rules, and the scope we agree on together. Depending on your property and local rules, outside specialists may be needed for work such as land surveys or septic design and installation.
WA/OR timeline example
- Permit packet prep
- 1 to 3 weeks
- WA/OR permit-review allowance
- 1 to 9 months
- Factory build (Battle Ground)
- 2 to 3 weeks
- Site prep, delivery & setup
- 12 to 16 weeks
WA/OR planning allowances. Confirm local permit and site-work schedules with the jurisdiction and site contractor.
Completed-project site benchmark
$41,000–$73,500
Middle 50% of invoiced field-service work across 236 completed projects in Regional benchmark (WA & OR). Records: 2023-01-09 through 2026-06-09.
Regional comparison only: these are not completed-project costs specific to your selected city or county. Delivery and crane pricing need a route and site review.
Washington & Oregon service area · All homes · 6 of 21 site items set
How this planning estimate works
Enter your address, city or ZIP code, then your lot conditions, then pick a floor plan. The calculator combines current home starting prices with field-work ranges from 236 completed Washington and Oregon projects (2023–2026). Use the itemized planning budget and local permit review window to understand the costs and steps to review for your property.
Free and open immediately with no email gate. For the underlying numbers behind the tool, see our local cost & timeline tables below, our model starting prices, and our Washington and Oregon cost guides.
- Homes built
- 650+
- Hours in our Battle Ground shop
- 430K
- Jurisdictions permitted
- 85+
- States served, incl. Alaska
- 7
Completed field-work ranges and permit timelines by area
Every Wolf home, from a backyard modular ADU to a primary residence, is built inside our Battle Ground, Washington factory under state-inspected IRC (International Residential Code) standards, so the price of the home itself stays consistent. What changes from city to city is the permit review window, local impact fees, and the site work required to prepare your foundation and connect utilities.
The table below shows what 236 completed Wolf projects (2023–2026) spent on site work, foundation, utilities, and permitting, with typical local permit review and field schedules. Those jobs were sold before our current delivery and setup prices took effect, so the low end of some ranges falls below today’s standard setup prices, which start at $35,500 outside Portland. The calculator above won’t go below the setup starting price for the model you pick. Permitting typically takes 1 to 9 months. Factory construction takes 2 to 3 weeks once your production slot begins. Delivery and setup take 12 to 16 weeks. These are stage allowances and can overlap.
| Jurisdiction / Area | Completed projects | Typical site & utility work (middle 50%) | Midpoint field work | Permit review window | Factory + site schedule |
|---|---|---|---|---|---|
| Clark County, WA Delivery route and site access priced per property | 61 projects | $18,500–$63,000 | $41,000 | 8 to 10 weeks Clark County permit review | 2 to 3 weeks factory · 12 to 16 weeks site & set |
| City of Portland, OR Delivery route and site access priced per property | 31 projects | $38,500–$55,000 | $47,000 | Up to 5 months City of Portland permit review | 2 to 3 weeks factory · 12 to 16 weeks site & set |
| City of Vancouver, WA Delivery route and site access priced per property | 8 projects | $40,500–$50,500 | $45,500 | 4 to 6 weeks City of Vancouver permit review | 2 to 3 weeks factory · 12 to 16 weeks site & set |
| Cowlitz County, WA Delivery route and site access priced per property | 10 projects | $42,000–$74,500 | $58,500 | 1 to 9 months WA/OR permit-review allowance | 2 to 3 weeks factory · 12 to 16 weeks site & set |
| Clackamas County, OR Delivery route and site access priced per property | 5 projects | $43,500–$48,500 | $46,000 | 1 to 9 months WA/OR permit-review allowance | 2 to 3 weeks factory · 12 to 16 weeks site & set |
| Skamania County, WA Delivery route and site access priced per property | 7 projects | $44,500–$58,000 | $51,500 | 1 to 9 months WA/OR permit-review allowance | 2 to 3 weeks factory · 12 to 16 weeks site & set |
| Mason County, WA Delivery route and site access priced per property | 6 projects | $65,500–$114,000 | $90,000 | 1 to 9 months WA/OR permit-review allowance | 2 to 3 weeks factory · 12 to 16 weeks site & set |
| Kitsap County, WA Delivery route and site access priced per property | 5 projects | $58,500–$88,000 | $73,500 | 1 to 9 months WA/OR permit-review allowance | 2 to 3 weeks factory · 12 to 16 weeks site & set |
| Washington & Oregon regional benchmark Delivery route and site access priced per property | 236 projects | $41,000–$73,500 | $57,500 | 1 to 9 months WA/OR permit-review allowance | 2 to 3 weeks factory · 12 to 16 weeks site & set |
Field-work figures cover site preparation, foundation, utility trenching, and permitting on completed Wolf turnkey builds (2023–2026) and exclude the home starting price. Individual lots with steep slopes, engineered retaining walls, long utility runs, or new septic systems can fall above the middle-half range.
Published home starting prices and standard setup baselines
Add the home starting price to standard delivery and setup for a combined baseline. Standard setup in Washington and Oregon includes specified foundation, trenching, and utility-connection work. Appliances, permit and utility fees, taxes, options, and work beyond that scope are separate. Your written proposal defines the work for your property.
Starting price is for the home unit only and excludes appliances, delivery, installation, permitting, and site work. You can purchase our appliance package or provide your own appliances. Final project pricing is based on your specific property and selections. Standard delivery covers sites within 20 miles of our Battle Ground factory. Delivery over 20 miles from our Battle Ground factory is priced per project.
| Model | Size & layout | Home starting price | Delivery & setup starting price | Combined baseline |
|---|---|---|---|---|
| Model E | 616 sq ft · 2 bd / 1 ba | $97,500 | $37,500 | $135,000 |
| Model F | 616 sq ft · 2 bd / 1 ba | $97,500 | $37,500 | $135,000 |
| Model B City of Portland only | 300 sq ft · 1 bd / 1 ba | $67,500 | $34,000 | $101,500 |
| Model I | 1,232 sq ft · 3 bd / 2 ba | $178,500 | $54,900 | $233,400 |
| Model J | 800 sq ft · 2 bd / 2 ba | $156,500 | $49,900 | $206,400 |
| Model K | 432 sq ft · 1 bd / 1 ba | $85,500 | $35,500 | $121,000 |
| Model L | 984 sq ft · 2 bd / 2 ba | $167,500 | $49,900 | $217,400 |
Phase 1 · 1 to 3 weeks
Site evaluation & submittal packet
After a signed agreement, we review the site requirements within your project scope and prepare the site plan and permit package.
Phase 2 · 1 to 9 months
Local permit review
Your city or county reviews the site plan while the factory building plans carry state modular approval.
Phase 3 · 2 to 3 weeks
Factory build
Once your production slot starts, your home is framed and finished indoors in Battle Ground.
Phase 4 · 12 to 16 weeks
Site prep, crane set & closeout
Site preparation, foundation, crane set, utility tie-ins, and final inspection overlap with the factory schedule.
Free ADU cost calculator FAQ
How does this ADU cost calculator work?
How accurate is the estimate?
Is the ADU calculator free?
What does the cost estimate include?
Can it tell me what an ADU costs in my city?
What does the free property evaluation cover?
Start with a preliminary property review
Our free preliminary study reviews zoning, setbacks, and what is generally allowed on your site. Paid project work begins after an agreement is signed and you choose to move forward.